|

Macway Uhl helped a major company
assess the political, environmental,
and regulatory risks involved in a
re-gasification facility to be sited
in a congested area.
Challenge
A U.S. based oil company along with
its international partners were
considering the development of a
re-gasification terminal at a site
with significant environmental and
regulatory challenges. They needed
to gain alignment with their
partners on how best to tackle a
variety of project challenges, on
how to prioritize regulatory
approval efforts, and on
expectations for achieving these
goals.
Solution
Macway Uhl conducted a schedule risk
analysis with the major partners.
Based on the deterministic schedule,
regulatory and other risks were
assessed, including the underlying
drivers of each risk and their
impacts on key milestones.
Insights were revealed about the
likelihood of each activity delaying
the project and risk management
plans were developed. These included
contracting philosophies, internal
approval processes, and project
execution strategies to both prevent
and mitigate adverse outcomes.
Results
- The analysis revealed that state
regulatory approvals actually
were quite unlikely to drive the
critical path of the project;
instead, key civil design work
needed additional focus as the
primary schedule driver
- By illustrating the importance
of pre-approval delays (which
the analysis indicated
represented 40+% of the schedule
risk), the partners re-focused
their efforts from construction
risk assessment towards their
own internal alignment and
approval processes
|